Key points
- SRK Consulting estimated an NI 43-101-compliant indicated resource of 63,000 carats at Diaz Prospect 1.
- Seventy-six per cent of the resource, or 48,000 carats, occurs at an average grade of 0.43 carat per square metre.
- Diamonds recovered in sampling were valued by the Namibian government at $318 (U.S.) per carat.
- DFI and Bonaparte will share mining revenue on a 70 per cent to 30 per cent basis under the short form agreement.
Diamond Fields International
Ltd. has commenced diamond
production in the indicated resource areas defined under the
previously announced joint operations agreement with Bonaparte Diamond Mines
NL after signing a mining agreement with Bonaparte.
DFI’s mining vessel, MV DF Discoverer, commenced mining operations on
Jan. 27, 2007, in the joint operations area in the Diaz prospect 1 (DP1) in
ML111 offshore Luderitz, Namibia, where independent consulting company SRK
Consulting has estimated a National Instrument 43-101-compliant indicated resource of
63,000 carats derived from sampling conducted under the joint operations
agreement with Bonaparte.
As previously announced, this indicated resource occurs within seven discrete
zones over a total area of 315,000 square metres in DP1 at an average grade of 0.2 carat per square metre,
but 76 per cent of the total resource (48,000 carats) occurs at an average grade of
0.43 carat per square metre in an area of 111,500 square metres. SRK anticipates that grades achieved during
mining could be up to 30 per cent higher than the estimates. The average size of the
diamonds in DP1 is estimated by SRK at 0.47 carat per stone (arithmetic mean), which is
significantly higher than displayed in most deposits delineated to date in the
Luderitz area. The diamonds recovered in sampling were valued by the Namibian
government diamond valuation process at $318 (U.S.) per carat.
The diamondiferous gravels generally lie at shallow depths with average
sediment thickness ranging from 0.5 m to 2.5 m, and so are conducive to high
production rates and lower unit costs.
DFI and Bonaparte have concluded a short form mining agreement to enable
both companies to benefit from the high diamond grades identified during the
late 2006 joint operations sampling program while a more comprehensive
agreement is concluded between the parties. In summary, the mining joint
operations will be conducted by DFI using its vessel MV DF Discoverer on a
70 per cent (DFI) to 30 per cent (Bonaparte) shared revenue and agreed operating cost basis. The
mining is being undertaken under an agreed mining plan and the full agreement
is expected to be completed within the next few weeks.
Details of the indicated resource calculation, including the key
assumptions, parameters and methods used to estimate the indicated resource,
are contained in the NI 43-101 technical report entitled, “Resource Estimates
for the Diaz Prospect 1, Namibia,” dated December, 2006, prepared by SRK for DFI
and Bonaparte, a copy of which has been filed under DFI’s profile on the SEDAR
website. Dr. A.E. Annels, who is responsible for the resource
estimates contained within the SRK report and is the designated qualified
person, has read and approved the scientific and technical information
contained in this news release.