Presentation Summarizing the BGR EIS Regarding Testing Impossible Metals’ Eureka III pilot collector

Key points

  • Impossible Metals and BGR announce the Eureka 3 pilot collector will not be ready for the early 2026 test as planned; the test is postponed to 2027 or 2028.
  • Eureka 3 is a 6,000-meter-rated AUV about the size of a 20-foot shipping container, with 11 collection arms, a four-ton payload capacity, 11-ton dry weight and roughly 90-kilowatt battery capacity.
  • The test plan calls for 20 collection cycles over four days in BGR’s Clarion Clipperton Zone contract area, comparing nodule removal rates of 50% and 90% to measure impact differences.
  • DHI’s plume modeling, based on an average spill rate of 0.05 kg/second, found 95% of suspended sediment redeposits within 7 days, with 93% remaining inside the mined area.
Previous Article

Odyssey Marine Exploration Appoints Larissa Pommeraud to its Board of Directors

Next Article

Landmark Deepsea Environment Moorings Successfully Deployed in the Cook Islands

Write a Comment

Leave a Comment

Your email address will not be published. Required fields are marked *

Subscribe to our newsletter

Ocean mining news, every Monday