Chatham Provides Korella North Mine Update

Key points

  • Queensland Treasury’s environmental security bond assessment for the Korella mine is expected to be completed by end of January 2025, and no on-site work can begin until it is posted.
  • The first on-site operation will be opening costeans to expose the 22-metre-thick Monastery Creek phosphate member for assessment with a hand-held XRF.
  • The nominated local mining contractor plans to use a 50-tonne hydraulic excavator to dig the costeans.
  • Chatham signed a representative agreement with Indonesian company Indevco, established in 1993, as part of its market development in Indonesia, and continues studying phosphate exports through the port of Karumba instead of Townsville.

Chatham Rock Phosphate Ltd. has provided an update on progress at the Korella North mine.

As earlier advised, the Queensland Treasury is in the process of assessing the environmental security bond for the Korella mine and this is now expected to be completed by end of January, 2025. Until and unless the bond is posted, no on-site activities can commence. With this period coinciding with part of the wet season, this will not of itself limit on-site activities.

Commencement of mining

The first on-site operation will be the opening of costeans to fully expose the 22-metre-thick Monastery Creek phosphate member to allow ground conditions to be fully assessed and to enable the individual plies to be analyzed using a hand-held XRF.

The about to be nominated local mining contractor has visited the site and determined that he will use a 50-tonne hydraulic excavator to dig the costeans. Selective mining of the individual plies will enable the immediate mining and screening to produce a saleable product. Ex mine sales of simply screened fine soft rock phosphate into the domestic market will generate immediate cash flow.

Phosphate market developments

Chatham has in the last weeks fielded an increasing number of enquiries for supply of lump phosphate, with Vietnam now joining China and Malaysia seeking immediate supply.

Lump phosphate is used in the production of yellow phosphorus that is the precursor for thermal grade phosphoric acid used in battery production. This premium product to be produced at Korella North has its value further enhanced since Korella phosphate has extremely low arsenic values, being on average less than one part per million (ppm).

The Korella North mine has the capability to produce the required product by a simple screening operation.

Transport logistics

Chatham has since September, 2023, studied the potential to export Korella phosphate through the port of Karumba, rather than port of Townsville.

The potential for Korella lump rock phosphate exports through a facility in the port of Karumba in the Gulf of Carpentaria is now under intensive study.

Marketing

Chatham has commenced market development in Indonesia, Australia’s nearest and largest market for crushed rock phosphate.

The signing of a representative agreement with leading Indonesian company Indevco is the first step in the company’s market development process. Exports through Karumba will provide shipping advantages for Indonesian fertilizer producers currently importing phosphate from overseas and local sources.

Shareholders will be kept informed of progress at the Korella North mine and the facility for export of lump phosphate at Karumba.

PT Indevco Internus (Indevco) is a leading Indonesian company established in 1993 with experience in the import of raw materials for fertilizer production in Indonesia and with current business activities, including export of fertilizers manufactured by Pupuk Indonesia.

Previous Article

Matariki FM - SBMA Commissioner Alex Herman & Ed Herman Update

Next Article

Diving Deeper: How seabed minerals could shape the Cook Islands’ future

Write a Comment

Leave a Comment

Your email address will not be published. Required fields are marked *

Subscribe to our newsletter

Ocean mining news, every Monday