Diamond Fields International Ltd. — Resource Development Progress and Vessel Update

Diamond Fields International Ltd. has received very encouraging results from

the recently completed resource development sampling conducted by Bonaparte

Diamond Mines NL (ASX: BON) under a joint operations agreement

and expects resumption of mining operations in early November.

The resource development sampling program by Bonaparte Bay in the joint

operations area in ML111, offshore Luderitz, was successfully completed in late

October. A total of 291 gem-quality diamonds weighing 135.92 carats were

recovered and the grid-based sampling results show near-continuous diamond

mineralization over a substantial cumulative area of approximately

290,000 square metres.

A total of 577 grid-based samples were taken of which 159 samples were

positive and multiple diamond recoveries (more than one stone) were made at 56

sites. Based on groups of closely associated positive results, a total of nine discrete zones of near-continuous mineralization covering a cumulative area of

approximately 290,000 square metres, have been identified.

SUMMARY OF RESULTS

Stones Carats

Diamonds Carats Size bigger than bigger than

Samples Positive Multiple () () range(ct) 0.4 ct 1 ct

577 159 56 291 135.92 0.07 to 6.46 127 14

(*) Incorporating 28 stones (9.32 carats) from 24 sites that were resampled for technical reasons

Sampling was undertaken on a grid of approximately 50-metre-by-40-metre spacing and

average sample size was approximately 2.6 square m. This is sufficient density for

estimation of National Instrument (NI) 43-101 and JORC compliant resources to the indicated category. In terms of the joint operations agreement Bonaparte has appointed

independent experts, Steffen Robertson & Kirsten (SRK) of Cardiff, United

Kingdom, to analyze these sampling results and carry out delineation, grade

estimation and classification of resources in compliance with the NI 43-101

and JORC codes. It is anticipated that their report will be completed by end

November, 2006.

Results of the sampling programs have been reviewed (including sampling,

analytical and test data) by Randal Cullen, PGeol, a qualified person as indicated under NI 43-101.

The company also reports that the engineering work program on its vessel

mv DF Discoverer is nearing completion. It is expected that the vessel will

return to Namibia and resume mining operations in early November.

Roger Daniel, president and chief executive officer, commented: “We are very pleased with the

results from the Bonaparte sampling operations which we expect to result in an

increase to our resource base and improve mine planning options. We are also

looking forward to the imminent resumption of marine diamond mining with our

own vessel and expect improved operating availability and efficiency following

the repair, maintenance and upgrade program.”

Previous Article

Diamond Fields International Ltd. - Annual Financial Statements Filed, Removal of Management Cease Trade Orders and Rights Offering Update

Next Article

Nautilus Applies for Mineral Rights Over Vast Areas of Seafloor

Write a Comment

Leave a Comment

Your email address will not be published. Required fields are marked *

Subscribe to our newsletter