Namibian revises outlook; Nam 2 results

Key points

  • First-half 2000 production was approximately 100,000 carats.
  • MV Oceandia was withdrawn from operation on June 1, 2000, as upgrading it was uneconomic.
  • Construction of the Nam 2 mining system is complete, with dry-land testing underway and commissioning expected in the fourth quarter of 2000.
  • Diamond prices averaged $184 (U.S.) per carat for the six months ended June 30, 2000, versus an expected $155.

Namibian Minerals has recorded its progress on its Nam 2 mining system and exploration

activities, and a revised production outlook for 2000.

Lower production levels continued in the second quarter as a result of

more difficult than expected mining conditions for the company’s major

production vessel, MV Kovambo, the extended time in port required to upgrade

MV Namibian Gem, and the decommissioning of MV Oceandia. Production for the

first half of the year was approximately 100,000 carats.

After initial testing of ODM areas in the first quarter, the NamSSol

mining system supported by MV Kovambo returned to mining licence 51. More clay

than expected was encountered in these mining areas, causing tracking

difficulties for the machine and reduced mining rates. NamSSol has since been

relocated to other parts of mining licence 51 which have easier mining

conditions but are of lower grade.

The new Nam 2 second-generation mining system has been specifically

designed to deal with these more difficult mining conditions with more

tracking power, reduced weight pressure, cutters and water jetting and it will

be used in the areas where NamSSol cannot operate. Mining of parts of mining

licence 51’s diamond resources has therefore been deferred until the arrival

of the new-generation machine.

Production was also affected by the extended time required to upgrade

MV Namibian Gem in the second quarter. A complete engineering overhaul was

required to bring the vessel up to necessary standards. The vessel spent 2.5 months in port, which was substantially longer than expected.

MV Namibian Gem returned to production in late June and production levels have

already benefited this quarter. To concentrate on continuous production, the

proposed minor modifications to MV Ivan Prinsep have been deferred until 2001.

MV Oceandia was withdrawn from operation on June 1 as the cost to upgrade her

was uneconomic.

With difficult mining conditions for NamSSol, a delay in production from

Nam 2 and the removal of one ODM vessel from production, the

company’s target production for 2000 will not be achieved. The revised

production estimate from three vessels is in the range of 225,000 to 250,000

carats. Higher-than-expected diamond prices ($184 (U.S.) per carat for six months

to June 30, 2000, against an expected $155 (U.S.) per carat will to some extent

offset the lower revenues from revised production estimates. Cash at June 30,

2000, was $13-million (U.S.).

“Mining conditions have proved harsher than expected. The year 2000 is now a year

of consolidation as we continue to expand our technology to handle the even

more rigorous mining conditions and geological settings. We look forward to

resumption of growth in 2001,” said chairman and chief executive officer, Alastair Holberton.

Construction of Nam 2 mining system complete

Construction of the new Nam 2 mining system is complete, and dry-land

testing began last week. Namco’s first marine mining system, NamSSol,

revolutionized the ocean diamond industry with its ability to pump high

volumes of seabed material using advanced dredging techniques. Further

innovations have been added to Nam 2, which is specially designed to

facilitate mining through thicker overburden and more challenging geological

terrain. Dry testing of Nam 2 will continue over the next two months.

Namco’s new mining vessel, MV Ya Toivo, which will provide the operating

platform for Nam 2, arrived in Cape Town from Poland on July 3. Since November,

1999, extensive modifications have been carried out on the former British navy

vessel including deck extensions, the installation of a four-point mooring

system, a helicopter deck and a dynamic positioning system and the

refurbishing of onboard accommodation. Conversion of the vessel, at owner’s

cost, took one month longer than scheduled. The 8,000-gross-ton MV Ya Toivo

will be one of the largest diamond mining vessels deployed off the Namibian

coast.

Installation of the 100-tons-per-hour processing plant on the MV Ya Toivo

began on July 5 and is expected to take 16 weeks to complete.

Commissioning is now expected to be completed in the fourth quarter of 2000.

Following commissioning of Nam 2 and MV Ya Toivo, a full year of

commercial diamond production is planned for 2001 from the four mining

vessels.

Sampling to start in third quarter

Sampling is on schedule to start this quarter using a new drilling tool

jointly designed by Namco and German engineering company, Wirth. Following

completion of 2,500 line kilometres of geophysics over selected parts of Mining

Licence 36 in April, MV Zacharias was converted for sampling. A helicopter

deck, 10-tons-per-hour processing plant and complete launch and recovery

system were installed. Results from the geophysics were encouraging, with many

new geological features identified for testing. The sampling tool’s unique

ability to operate in a wide range of ocean floor conditions and to determine

the precise nature of the mining conditions such as sediment composition, clay

and minability, will enable the optimum mining systems to be allocated to

different parts of Namco’s concessions.

“The start of a continuous sampling program is one of our most

significant milestones. This tool will allow us to develop the full potential

of our ocean diamond resources,” said Mr. Holberton.

Second quarter and half-year financial results will be published in mid-August.

Previous Article

Namibian Minerals increases dividend in first quarter

Next Article

Namibian earnings drop in second quarter

Write a Comment

Leave a Comment

Your email address will not be published. Required fields are marked *

Subscribe to our newsletter