Sunda Shelf exploration update

Processing of the first section of the 37840 cubic metre bulk

sample of basal gravels from the south channel, bulk sample site

1, of the company’s Sunda Shelf diamond exploration project in southeast Kalimantan, Indonesia, has begun.

The plant is currently processing the first 2360 cubic metres of

gravels from sub-sample 1A. This should be completed during the

next few days with results of diamond recovery expected to follow

shortly after.

The 30 cubic metre per hour jig plant and Wolf X-ray diamond

recovery machine have been commissioned with sandy gravels dug

from a barren area immediately prior to the commencement of the

main sample. It is planned to double the capacity of the plant

during the next two months.

Large gravels of up to 15cm in diameter – an encouraging indicator

for the presence of diamonds – have been mined in the first

section of the sample.

Details of the sample program follow.

South Channel Sample – Line 2000 West (Site 1)

The sample of 37,840 cubic metres of gravels is being mined on

line 2000 west, between 1835 south and 1550 south. It will be

extracted and processed in five sub-samples and should be completed

by the end of January.

Trench

Length Gravel Overburden

Sub- at bedrock Volumes volume

Sample (m) (cubic m) (cubic m)

—— ———- ——— ———-

1A 25 2,360 38,600

1B 90 14,400 89,900

1C 60 7,460 60,000

1D 80 11,100 80,000

1E 30 2,520 30,000

Maximum basement depth over the length of the channel is 35.5

metres below sea level. This is within the digging reach of the

Aokam Thai No 3 dredge.

Sub-Sample 1A

The dredge removed 36,000 cubic metres of mud and

clay to reach the target area at 30 metres below sea level. It

then stripped overburden of 38,600 cubic metres to

expose the gravel surface area of 25 metres by 25 metres. The

gravel thickness of the first sub-sample is 4 metres

and the volume to be mined and processed is 2,360 cubic metres.

All gravels in the minus 18mm size fraction are being processed

through the jig plant. The final diamondiferous concentrate is

processed by a Wolf X-ray diamond recovery machine. Tailings from

the X-ray recovery will be processed by Plietz jigs to recover

heavy minerals and audit the efficiency of the X-ray process. The

screens of the jig plant are set to process gravels in the minus

18mm range which will allow all diamonds up to 60 carats in size

to be recovered. The jig baskets will be removed progressively

over the next few days to enable the concentrate to be processed

by the X- ray machine. Results of diamond recovery from

sub-sample 1A will be released as soon as available. This is

expected to be by the end of the first week of December.

The gold, platinum and heavy mineral concentrates will be

processed at the onshore laboratory of the project’s exploration

manager, P.T. Indo Mineratama.

The sub-sample 1A gravels are of a favourable size with oversize

of up to 15cm in diameter, indicating sufficient energy having

been active within the palaeochannel system to have transported

diamonds to the present location. This is further supported by

the presence of gold and rutile – key regional indicators for

diamonds – in the commissioning sample.

Sub-Samples 1B to 1E

These samples will be mined and processed during the next two

months and results will be announced progressively.

The sites of three further samples have been selected and each

will be infill drilled prior to sampling.

Previous Article

Appeal against Benco unsuccessful

Next Article

Shelf diamond project progress

Write a Comment

Leave a Comment

Your email address will not be published. Required fields are marked *

Subscribe to our newsletter