Test Early, Test Often: Real-World Prototyping for the Eureka III System

Key points

  • Jason Gillham, CTO/COO and co-founder of Impossible Metals, demonstrates a wooden mockup of the Eureka III system built to test hardware design decisions before finalizing them.
  • The mockup’s main box represents a hopper with battery compartments, with a distribution box mounted at the top.
  • The team uses string on the physical mockup to work out cable routing and connections, making final decisions on cable links rather than relying solely on CAD models.
  • Gillham says the hands-on approach reflects a test early, test often philosophy aimed at reducing uncertainty and validating design assumptions.
Previous Article

Thorium Tracing

Next Article

Copperhead Resources Announces Changes in Officers

Write a Comment

Leave a Comment

Your email address will not be published. Required fields are marked *

Subscribe to our newsletter

Ocean mining news, every Monday